WhiteFiber

#16of 51 neoclouds · score 19.3/100

Listed AI cloud and colocation provider reporting revenue obligations separately from future colocation lease payments. Its NC-1 contracted IT capacity is now online. Sources below.

PublicUS

Verified

Visit WhiteFiber Compare with neighbours Request GPU capacity

How WhiteFiber scores

Weights and formula
SignalValuePointsWeightAdds
ClusterMAX tier Underperforming 15.0 30% 4.5
Contracted power 40 MW 20.0 20% 4.0
Contracted backlog $729M 20.0 15% 3.0
Capital raised $310M 52.0 15% 7.8
GPUs Not disclosed 0.0 10% 0.0
Named customers Not disclosed 0.0 10% 0.0
Composite score (rank #16 of 51)19.3

This dataset has no verified GPUs or named customers, so those signals score 0. A sourced figure sent to hello@neocloudrankings.com goes straight into the next build.

Signals and facts

Source per value
ClusterMAX Tier in SemiAnalysis ClusterMAX 3.0 (23 Sep 2026), the public hands-on rating of GPU clouds. Medal tiers run Platinum, Gold, Silver, Bronze; Participation Ribbon sits between Bronze and Underperforming. Underperforming and Unavailable are the two groups SemiAnalysis lists under "Not Recommended": Unavailable covers providers it could not test or judged too small to rate. Empty when the provider is not listed.
Underperforming 2
Contracted power MW Power the company states as contracted, secured or committed in its portfolio, in MW. Speculative pipeline and planned campuses are excluded; the power note quotes the company's own word for it.
40 1
Active power MW Power the company states as active, live, operational or managed today, in MW.
40 1
Power note What the power figures cover, the as-of date, and targets or planned campuses that are not counted.
NC-1: all 40 MW of contracted IT capacity online and billing by the 10 Nov 2026 release; this is a site subtotal, not a group-wide power total. NC-2/NC-3 development potential excluded. 1
Backlog $M Contracted revenue backlog, remaining performance obligations or total contracted value as the company states it, in USD millions.
729 1
Backlog note Which backlog measure the company uses and its as-of date.
ASC 606 RPO of $729.0M at 30 Sep 2026. Separate ASC 842 future lease payments of $421.5M are excluded; those payments also exclude NC-1’s remaining 20 MW because that lease had not commenced at quarter-end. 1
Quarterly revenue $M Latest reported quarterly revenue, in USD millions, from the company's results release or filing. Company-level unless the note says otherwise.
24 1
Stated ARR $M Annualized run-rate revenue exactly as the company states it, in USD millions. We never annualize a quarter ourselves.
Not published
Revenue note Period, basis and any revenue targets the company has stated.
Q3 2026 group revenue $24.0M, including Cloud Services $18.1M. The approximately $365M annualized portfolio revenue is a mid-2027 deployment target, not current ARR. 1
GPUs GPUs deployed, owned or under contract as the company states it.
Not published
GPU note What the GPU figure counts and when it was stated.
Not published
Capital raised $M Equity and debt raised, in USD millions: the total when the company states one, otherwise the rounds and facilities named in the capital note.
310 1
Capital note Exactly which rounds, notes or facilities the capital figure covers, with dates.
Completed $310M gross convertible notes due 2032 in Aug 2026; approximately $298.5M net proceeds. This is one offering, not cumulative funding. New $300M NC-1 facility excluded because initial funding was still conditional at release. 1
Customers Customers named publicly by the company, in its filings or in reputable press.
Not published
Ownership Publicly listed, privately held, or a subsidiary of another company.
public 1
Ticker Exchange and ticker symbol for listed companies.
NASDAQ: WYFI 1
Parent Owner or majority shareholder when the neocloud is part of another group.
Not published
Quarterly capex $M Latest disclosed quarterly capital expenditures, in USD millions. Context only; excluded from the composite score.
Not published
Capex note Period and scope of capital expenditures, including whether figures are actuals or guidance.
Not published
GPU models Hardware advertised or tested, with reservations and future availability explicitly noted. Context only; not a fleet count or scoring input.
Not published
Operating footprint Company or service geography as sourced; a general cloud footprint does not guarantee GPU stock in each region.
Not published
Deployment and orchestration Available provisioning and cluster management services; future features are labelled as such.
Not published
Cluster interconnect Published cluster network technology or bandwidth; not a measured service-quality claim.
Not published
Capacity scope Partner supply, network coverage and other non-fleet capacity signals excluded from GPU scoring.
Not published

Sources

  1. WhiteFiber-issued Q3 2026 results, 10 Nov 2026 (PR Newswire) accessed 2026-11-11
  2. SemiAnalysis ClusterMAX 3.0, 23 Sep 2026 accessed 2026-11-11

Get GPU capacity from WhiteFiber and similar neoclouds

Tell us what you need once. We send it to matching neoclouds and they reply to you directly.

Quote requests open shortly. To get in first, email hello@neocloudrankings.com.